1. DCL-56 Old River Cherwell Underbridge Renewal
Complete multidisciplinary engineering for replacing the critical DCL/56 bridge over the flood-prone River Cherwell. Deliverables included Structures Form A and Form B, AFC drawings, Permanent Way GRIP 4/5 track alignment integration, and geotechnical GIR/GDR reports.
Engineering Challenge & Solution: Piles met unexpected refusal early during installation; FJD re-engineered the foundation capacity in real time, liaising with CAT 3 checkers without delaying the blockade. Supported Environment Agency flood modelling and resolved all site TQs within 72 hours. The 240-tonne deck was smoothly installed using two rail-mounted Kirow cranes.